Innovative technology 1400- 3000 m

The cableway Sölden heralds a new era. 

The cableways Sölden convince by trendsetting technologies and innovative planning throughout the last decades.

Now a new era has begun with new architecture from the valley up to 3000 m altitude.

Impressions

Start of work peak: A building time of 9 months is needed for the 3-S-cableway. But there are only 5 months for working on 3.054 m altitude. That's why the basement of the new upper station is already built in summer 2009.

Start of work station building: From April 13th 2010, the executive companies go on working on the operation buildings (base station, middle station and upper station) and the cable way technique.

Starting: beginning winter season 2010/2011
Investment: 35 million Euro
Cable way technique: Doppelmayr
Planning: architecture office DI Johann Obermoser, Innsbruck